Court sets hearing on SWEPCO plant

By The Associated Press

This article was published February 9, 2010 at 12:05 p.m.

The Arkansas Supreme Court is to hear oral arguments on April 15 in a utility’s appeal of a ruling that voided its permit to operate a $1.6 billion coal-fired electric generation plant in southwest Arkansas.

Southwestern Electric Power Co. is challenging a ruling by the Arkansas Court of Appeals that found that the state Public Service Commission didn’t follow proper procedures before issuing a permit.

The plant is under construction near Fulton in Hempstead County, where nearby landowners challenged the permit in court.

The Arkansas Pollution Control and Ecology Board ruled last month that SWEPCO was properly granted a separate air quality permit.

Comments on: Court sets hearing on SWEPCO plant

To report abuse or misuse of this area please hit the "Suggest Removal" link in the comment to alert our online managers. Read our Terms of Use policy.

Subscribe Register Login

You must login to make comments.

Top Picks - ARPreps
Arkansas Online