OIL AND GAS REPORT

The Arkansas Oil and Gas Commission last week issued 1 drilling permit, 0 well completions and 8 well recompletions. By county, they were:

DRILLING PERMITS

COLUMBIA --

O'Brien Energy Co. of Shreveport, LA for Cypress Creek No. 6 1-H to TVD: 5,563 ft. and MD: 13,000 ft. in Pettett Form. of Pisgah Fld. Loc. SHL: 2,146 ft. FNL & 2,418 ft. FEL and PBHL: 2,018 ft. FNL & 100 ft. FEL of Sec. 6-20S-20W. Contractor: Basin Drilling; work began Nov. 15.

WELL COMPLETIONS

WELL RECOMPLETIONS

CLEBURNE --

XTO Energy Inc. of Oklahoma City for Hooten No. 2-18H, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 7,395 ft., perf. 3,050-7,262 OA ft. Loc. SHL: 209 ft. FSL & 1,105 ft. FEL and BHL: 460 ft. FNL & 1,128 ft. FEL of Sec. 18-10N-8W. Workover done Oct. 5.

XTO Energy Inc. for Moss No. 1-14H, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 6,933 ft., perf. 2,710-6,822 OA ft. Loc. SHL: 240 ft. FSL & 1,705 ft. FWL and BHL: 482 ft. FNL & 1,185 ft. FWL of Sec. 14-11N-9W. Workover done Oct. 3.

FAULKNER --

BHP Billiton Petroleum (Fay) of Houston for Poczik No. 8-11 1-23H26, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 9,590 ft., perf. 6,400-9,477 OA ft. Loc. SHL: 2,370 ft. FNL & 2,029 ft. FWL and BHL: 1,357 ft. FNL & 2,478 ft. FWL of Sec. 23-8N-11W. Workover done Sept. 19.

BHP Billiton Petroleum (Fay) for Poczik No. 8-11 2-23H26, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 9,867 ft., perf. 6,290-9,741 OA ft. Loc. SHL: 2,355 ft. FNL & 1,959 ft. FWL and BHL: 1,098 ft. FNL & 1,888 ft. FWL of Sec. 23-8N-11W. Workover done Sept. 19.

WHITE --

BHP Billiton Petroleum (Fay) for George Morris No. 8-7 1-27H34, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 10,408 ft., perf. 5,308-10,313 OA ft. Loc. SHL: 768 ft. FSL & 587 ft. FWL and BHL: 486 ft. FSL & 567 ft. FWL of Sec. 27-8N-7W. Workover done Sept. 25.

BHP Billiton Petroleum (Fay) for Hastings No. 8-6 2-21H, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 9,832 ft., perf. 5,650-9,732 OA ft. Loc. SHL: 284 ft. FSL & 265 ft. FWL and BHL: 480 ft. FNL & 1,154 ft. FWL of Sec. 21-8N-6W. Workover done Sept. 22.

BHP Billiton Petroleum (Fay) for Hays No. 8-6 1-18H, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 8,576 ft., perf. 4,876-8,473 OA ft. Loc. SHL: 1,135 ft. FSL & 2,417 ft. FEL and BHL: 4,678 ft. FSL & 4,457 ft. FEL of Sec. 18-8N-6W. Workover done Sept. 22.

BHP Billiton Petroleum (Fay) for Morris No. 8-7 1-27H, 24-hr. prod. not available in Fayetteville Form. of B-43 Fld. Drilled to TD: 9,110 ft., perf. 5,170-8,922 OA ft. Loc. SHL: 839 ft. FSL & 591 ft. FWL and BHL: 480 ft. FNL & 585 ft. FWL of Sec. 27-8N-7W. Workover done Sept. 25.

ABBREVIATIONS

Loc. -- location; Perf. -- perforations; FEL -- from the east line; FNL -- from the north line; FSL -- from the south line; FWL -- from the west line; FEUL -- from the east unit line; FWUL -- from the west unit line; FNUL -- from the north unit line; FSUL -- from the south unit line; MCF -- thousand cubic feet; bbl -- barrel; MD -- measured depth; TD -- total depth; TVD -- true vertical depth; PBTD -- plug back total depth; BHL -- bottom hole location; PBHL -- proposed bottom hole location; SHL -- surface hole location; OA -- overall; N/A -- not available.